This course covers the full Manufacturing module in Quickenerp. Learn how to create and manage bills of materials, manufacturing orders, routing plans, work center operations, subcontracting, planning, and production reporting.

Responsible System
Last Update 07/21/2026
Completion Time 3 days 22 hours
Members 1
Inventory & Manufacturing
Manufacturing Overview
View all
New Content
Production Planning & MRP
Production Planning & MRP
Preview

Production Planning

Replenishment-Based MO Creation

Products with route "Manufacture" and a reordering rule trigger MO creation:

  1. Go to Inventory > Master Data > Reordering Rules.
  2. Set route = Manufacture.
  3. When stock drops below minimum, the replenishment engine creates an MO.

Planned Orders

Go to Manufacturing > Planning > Planned Orders. These are tentative MOs not yet confirmed. Review and confirm them in batch. Useful for medium-term capacity planning.

MRP (Material Requirements Planning)

For advanced planning:

  1. Go to Manufacturing > Planning > MRP.
  2. Click Run MRP.
  3. Quickenerp analyzes:
  • Current stock levels.
  • Open sales orders.
  • Forecasted demand.
  • Reordering rules.
  • BOM structure (explodes multi-level BOMs).
  • Generates proposed MOs and purchase orders.
  • Review and confirm the proposals.
  • Production Scheduling

    The Gantt view in Manufacturing Orders shows scheduled MOs across work centers. Drag and drop to reschedule. Filter by work center, date, product.

    New Content
    Creating, Confirming & Completing MOs
    Creating, Confirming & Completing MOs
    Preview

    Manufacturing Orders

    Go to Manufacturing > Operations > Manufacturing Orders.

    Creating an MO

    1. Click Create.
    2. Product - Finished good to produce.
    3. Quantity - Number of units.
    4. BOM - Auto-selected if only one BOM exists for the product.
    5. Routing - Auto-selected from BOM.
    6. Deadline Start - When production should begin.
    7. Deadline End - When production should be complete.
    8. Source Document - Auto-filled if created from sales order or reorder.
    9. Click Save.

    MO Lifecycle

    Status Meaning
    DraftMO created but not yet confirmed.
    ConfirmedMO is ready. Raw materials are reserved.
    In ProgressProduction has started (first operation logged).
    DoneAll operations complete. Finished goods in stock.
    CancelledMO is cancelled. Reserved material is freed.

    Confirming & Starting Production

    1. Click Confirm Production - Reserves raw materials.
    2. Click Plan - Assigns work orders to work centers.
    3. Click Start Production - Begins the first operation.
    4. Operators record time per operation.
    5. Click Record Components to register component consumption (if consuming manually).
    6. When all operations done, click Produce - The MO is completed.
    7. Finished goods appear in the WH/Stock location.

    Work Orders

    Each routing operation creates a work order. Open MO → Work Orders tab. Each work order shows:

    • Assigned work center and operator.
    • Scheduled start and end.
    • Components consumed at this operation.
    • Actual duration vs planned.

    Mark each work order as done by clicking the Complete Last Operation button on the MO.

    New Content
    Manufacturing Analysis & Cost Reports
    Manufacturing Analysis & Cost Reports
    Preview

    Manufacturing Reporting

    Manufacturing Analysis

    Go to Manufacturing > Reporting > Manufacturing Analysis. Pivot table with:

    • Dimensions: Product, BOM, Work Center, Operation, Vendor (for subcontracting), Date.
    • Measures: Quantity Produced, Planned Quantity, Duration (hours), Cost, Scrap Quantity.
    • Filters: Order Status, Date Range, Product Category.

    Cost Analysis

    Open a completed MO → Cost Analysis button. See:

    • Raw Material Cost - Sum of all consumed components - cost price.
    • Operation Cost - Time spent at each work center - hourly cost.
    • Total Cost - Material + Operations.
    • Unit Cost - Total Cost / Quantity Produced.

    Work Center Performance

    Go to Reporting > Work Center Performance. See for each work center:

    • Planned hours vs actual hours.
    • OEE percentage.
    • Load rate (scheduled hours / available hours).
    • Number of MOs processed.

    Best Practices

    • Review work center load weekly to avoid bottlenecks.
    • Track scrap percentage per product to identify quality issues.
    • Compare actual vs planned costs to improve BOM accuracy.
    • Use OEE to identify underperforming work centers.
    This documentation is updated continuously. Some features described here may be renamed, deprecated, or still being finalized.